Renewable energy in the Albanian market

How renewable plants still create an hourly position on ALPEX, still need a BRP, and still create imbalance when the forecast is wrong. Support rules live in Law 24/2023 and ERE acts, not on the trading screen.

Official source
Renewable-energy participation in the organised electricity market
Source language
Albanian
TradingDesk explanation
English

Why it matters

Most Albanian desks run hydro, solar or wind. Those plants do not sit outside the market. They still have a day-ahead shape, an intraday revision and a metered actual.

Support schemes, priority dispatch or licensing classes, if they exist, come from Law 24/2023 and secondary ERE decisions. They do not cancel imbalance. A plant that was paid a support price can still leave its BRP with a deviation bill.

Forecast quality is the operational problem. Legal status is the structural one. The desk needs both.

How it works

Official source: the renewable-energy law and any ERE license or support decision attached to the plant. TradingDesk explanation: the hourly chain is the same as for other generation.

Before D-1 the desk forecasts production, builds a day-ahead position on ALPEX if the participant trades there, and nominates the plan through the BRP.

On the day, weather and water change the output. Intraday is the last organised place to move volume. After real time, meters close the story. The difference versus the schedule is imbalance under the balancing rules.

Aggregation is common: many small RES sites, one balancing group. The forecast must use that same perimeter.

Article-level support tariffs and priority rules wait for the official PDF. This page will not invent them.

Key rules / parameters

ItemDetail
Legal parentLigji nr. 24/2023, plus the sector law where it applies
Market chainForecast, ALPEX where used, nomination, meter, imbalance
Responsible partyThe BRP of the group that contains the plant
Support vs imbalanceA support scheme does not replace balancing settlement
Official numbersOnly from the act, the license or the ERE decision
Official RES law PDFLigji nr. 24/2023, attached on this page
Self-producers PDFMIE Instruction 3/2019, see that Wiki page

TradingDesk context

TradingDesk Forecasting is the product view of this page. Wiki keeps the Albanian rule wrapper: RES is still a position, still a BRP, still an imbalance.

Source authority
Source: Republic of Albania / ERE
Publication date
2023-03-23
Official title
Ligji nr. 24/2023, datë 23.3.2023, për energjinë e rinovueshme
Source language
Albanian
Last updated
2026-09-10
Official source

ligj_nr._24_dt._23.3.2023.pdf

Download official PDF

renewable · RES · forecast · imbalance

Related official PDFs

Related